Modernization of elevator PLC equipment

Link:
Year:
2014
Technologies:
- operator station PC, WinCC 7.2; - сontroller SIMATIC S7-412-2PN, SIEMENS; - distributed peripheral devices (I/O signal system) SIMATIC ET200M, SIEMENS;Multiple - data acquisition station – SIMATIC S7-300 ET200M, SIEMENS; - operator station PC, WinCC 7.2; - low voltage complete device – SIEMENS, PHOENIX CONTACT; - data transmission networks – Profibus DP, Industrial Ethernet.
Project status:
Completed
About the project:
Modernization of elevator PLC equipment

 

Development of design and software documentation for modernization of elevator PLC equipment. Modernization of elevator PLC equipment

Amount of work:

  • Paternoster, separator, valve, reversing valve, distributor, conveyor, auger conveyor, sweep auger, ventilation unit, rotary valve, filter, compressor control;
  • Silo charging/discharging control;
  • Route control.

Scope of work:

  • Development of design documentation:
    - automation – designing automated technical processes – stage “Working project”;
  • Software development;
  • Onsite assembling;
  • Commissioning of the automation and control system;
  • Operating and technical personnel training;
  • Experimental-industrial commissioning (72 hours);
  • Commissioning.